Project Update – May 2022
Steel is completed and the metal decking is nearly completed. The concrete at the first floor is expected to be poured May 28. Work at the second floor will immediately follow. Construction of the stair towers is underway. The site work is ongoing. The infiltration fields are completed and the underground site utility work is ongoing.