Project Update – July 2022

The exterior wall framing and sheathing has progressed well. Concrete block work at stairs and detention area is nearing completion. Interior framing and roughing-in of systems is well underway on all three floors. Utility connections in the street are ongoing.

lower-parking-level

Image 5 of 8