Project Update – January 2023

The installation of the exterior bricks has been completed and the work is wrapping up on paneled siding.  Window installation is ongoing. Construction of the site walls is ongoing, but most of the exterior work will be performed in the spring. Insulation at the lower level ceiling is ongoing. The wallboard work is nearly complete, and the priming and painting of the walls is well underway.  Ceiling grid installation is ongoing and the mechanical, electrical, plumbing and fire protections systems are being installed to meet the ceilings. Ceramic tile work is in progress.