Project Update -February 2023

Work exterior is wrapping up on paneled siding and window installation. Construction of the site walls is ongoing, as is the site drainage work as weather permits.  The interior wallboard essentially complete, as is the first coat of paint on the walls is well underway.  Ceiling grid installation is ongoing and the mechanical, electrical, plumbing and fire protections systems are being installed to meet the ceilings. Doors and ceiling are being installed in the detention area. Millwork installation to start the week of February 6.