Project Update – May 2021

May 2021

This month, the 75% CD estimates were reconciled with values for each trade agreed upon. This cost information will help drive design decisions as we develop the 100% CD bid set. The contractor prequalification process continues, all Statement of Qualifications (SOQs) were due on May 5, 2021. The review process began of all qualifications for each potential bidder. Over 12 General Contractors and 101 Subcontractors submitted qualifications.  There were less than three submissions for Acoustical Tile and Elevator, and therefore these two trades were re-advertised and reviewed.